Function: By architectural and functional renewing of the existing flood plain system.
Construction Program: Preparing architectural, static, mechanical and electrical projects of 3.795 meter length and 15 meter width part of the Hydropark being constructed and turn — key completion of asphalting, irrigation system, children playgrounds, sitting banks, pedestrian brideand walking paths
Mechanical: Flood plain water pomps (2.000m3/h, 60mms) and flow control systems.
Electrical: Field and road illumination systems.
Environmental Design: Forestation, sodding, walking paths, bridges, playgrounds, field drainage systems and roads.
Date of the Contract: 2005
Completion Date: 2006